2007/07/18

Exploitable result, Track "Green Machines"

There has been published the first 'Exploitable Result' concerning to the Track 1, "Green Machines" of the project: 'Altenative process for manufacturing of aeronautical structural parts'

It try to cover two objectives:
  • Primary objective: reduce dramatically the enviromental impact of the manufacturing process of the structural parts present int he aeronautic sector.
  • Secondary objective: development of a manufacturing process and machine to fullfill the environmental requirements
Its current status is:
  • Alternative manufacturing process based od friction stir welding (FSW) under development: test part defined and start of the definition of the manufacturing process
  • Building of machine to support the FSW process: machine architecture defined and definition of critical machine components started.
Fatronik is the responsible of this exploitable result.